Australia declares NBN "built and fully operational"

Paul Fletcher, Australia's Minister for Communications, Cyber Safety and the Arts, has declared the National Broadband Network as " "built and fully operational." Thedeclaration is one of the steps that must occur under the NBN Companies Act before NBN Co can be privatised, but does not automatically trigger any further steps and the government has stated that it does not intend to consider privitisation during this term of Parliament.

Minister Fletcher stated that his formal declaration is based on a number of factors, including:

  • The number of premises able to connect to the NBN is over 11.86 million premises
  • At NBN Co’s FY20 results announcement in August 2020 there were around 100,000 complex premises yet to be made ‘ready to connect’ (RTC), that number has now reduced substantially and is expected to be around 35,000 as at 31 December 2020
  • New premises are being built all the time. This means that there will always be a number of premises around Australia that are not yet ‘ready to connect’. The fact that there is a certain number of premises which are not ready to connect is not of itself evidence that the network cannot be treated as ‘built and fully operational.’

“In my view the evidence before me shows it is appropriate to make the declaration that the NBN should be treated as built and fully operational’, Minister Fletcher said.

"Of course the government recognises that there are some premises which have not yet been made ready to connect – and I expect NBN Co to work as speedily as possible to make the network available to those premises.

"The government also recognises that there is continuing work to enhance the capabilities of the network. Earlier this year we announced a $4.5 billion upgrade to the NBN; the work to deliver that upgrade will be carried out over several years.

"Also, in some areas the NBN can only operate at full speed once all legacy copper services are migrated to an NBN or alternative service, which typically takes 18 months from when the NBN commenced services in an area. To minimise interference to the legacy services of other carriers during this period, the NBN operates with reduced signal power which reduces network speeds.

"But this doesn’t mean that NBN Co will stop developing. I fully expect that the Company will operate as a mature entity through continual improvement in the provision of quality services to its broadband retail customers, and ultimately to Australian households and businesses, as well as driving efficiency in its operations.

"As with all large telecommunications networks, NBN Co will need to keep investing in additional network capacity, extend its network to connect new developments and remediate technical issues as they arise."

https://minister.infrastructure.gov.au/fletcher/media-release/nbn-declared-built-and-fully-operational


Australia's NBN Co pushes fiber deeper and advances HFC network upgrade

NBN Co is pushing fibre deeper into communities in selected metropolitan and regional areas of New South Wales, Victoria, Queensland, South Australia and Western Australia. The fibre deeper work will pass more than 100,000 premises in areas currently serviced by Fibre to the Node (FTTN) technology, effectively converting FTTN locations to FTTP. NBN Co said it will consult with Internet retailers before finalising the design for its extended fibre network.

This marks the start of NBN Co’s $4.5 billion network investment program, which aims to make nbn’s highest wholesale speed tiers available, as demand arises, to around 8 million premises – or up to 75 percent of homes and businesses on the fixed line network by 2023.


NBN Co also reports that it is making good progress on its Hybrid Fibre Cable (HFC) network upgrade program. The company now expects to offer download speeds of 500 Mbps to close to 1 Gbps to approximately 625,000 premises, or around 25 percent of the HFC network footprint by November 2020.

NBN Co also reports that it is making good progress on its Hybrid Fibre Cable (HFC) network upgrade program. Since the company launched its nbn Home Fast, nbn Home Superfast and nbn Home Ultrafast wholesale speed tiers in May 2020, 100 percent of customers connected via HFC have been able to order nbn Home Fast; approximately 70 percent have been able to order nbn Home Superfast, and approximately 7 percent of customers in the HFC footprint have been able to access the fastest residential speed tier1.