Citing continue demand from customers for more space, Interxion announced expansions of its data centres in Amsterdam and Zurich.
- AMS 5.4 will add 1,000 square meters of equipped space and will add an additional 2 MW of available customer power. The capital expenditures for this expansion are expected to total approximately EUR 12 million. AMS 5.4 is scheduled to open by the end of Q4 2012.
- ZUR 1.3 will add 600 square meters of equipped space and will access existing customer power. The capital expenditures for this expansion are expected to total approximately EUR 4 million. ZUR 1.3 is scheduled to open by the end of Q4 2012.