Monday, January 30, 2023

NTT deploys Liquid Immersion Cooling at its new Mumbai data center

NTT Ltd., e of the world’s top 3 data center service providers, is deploying Liquid Immersion Cooling (LIC) and Direct Contact Liquid Cooling (DCLC) technologies at its Navi Mumbai Data Center. India becomes the first country across NTT’s global data center platform to deploy these alternative cooling technologies.

The one-of-its-kind facility is part of its Mahape campus, which has a capacity of 4.8 MW spread over 13,740 square feet area built. The campus is planned with the capacity for up to 4 data centers, reaching up to 150 MW of IT load. 

Speaking about this, Mr Sharad Sanghi, Managing Director of NTT Ltd. in India & Acting Senior Executive Vice President, Data Center and Marine Cable, NTT Ltd. said, “At NTT, we are guided by the principle of universal wellness, a people-first approach for our own personnel, the communities we operate in, and the overall global environment. The deployment of green data center technologies as demonstrated by this facility is going to be a tremendous validation for alternative cooling technologies. As India’s largest data center operator, we recognize the impact that DCLC and LIC cooling can have in significantly reducing the power consumption in future data centers. By successfully integrating these advanced processes, we have taken another step in building a connected future in a sustainable and responsible manner on a global scale.”

NTT Ltd. expands its global data center ambitions

NTT Ltd.’s Global Data Centers division is preparing to launch new data center capacity in India, the UK, Japan, USA, Germany, Malaysia and Indonesia.  When fully complete, these data centers will provide over 400 megawatts (MW) of IT load across these markets. Plans include:a Mumbai, India – NTT Ltd. will go live with its new Mumbai 7 Data Center by Q3 2020 in its Chandivali campus. The Mumbai 7 Data Center will offer 25 MW of IT load....


Monday, December 19, 2022

Oracle opens cloud region in Chicago

 Oracle opened its 41st global region and fourth in the U.S. in Chicago, Illinois.

The new Chicago region will offer over 100 OCI services and applications, including Oracle Autonomous Database, MySQL HeatWave, OCI Data Science, Oracle Container Engine for Kubernetes, and Oracle Analytics.

Oracle said its new facility has been designed to enable high availability, data residency, and disaster protection. OCI offers layers of security to help ensure resources are provisioned securely for every customer, a zero trust architecture for maximum isolation of customer tenancies, and many integrated customer security services that are offered at no extra charge.

In addition, the Oracle Cloud Chicago Region is designed to help meet the security and compliance needs of customers in both the commercial and public sectors. OCI’s architecture is designed to allow cloud regions to be deployed within separate secure and isolated realms for different uses. The Chicago area is the location of an existing Oracle Cloud Region with DISA Impact Level 5 authorization for use by U.S. government organizations to store and process Controlled Unclassified Information (CUI) and National Security Systems (NSS) information. Oracle currently operates several independent realms serving the U.S. and U.K. governments, and Oracle has announced that it plans to offer a sovereign cloud realm for the European Union in 2023.

“As the home to more than 20 percent of the Fortune 500, 60 percent of all U.S. manufacturing, and the world’s largest financial derivatives exchange, the U.S. Midwest is a global innovation hub across key industries,” said Clay Magouyrk, Executive Vice President, OCI. “These industries are increasingly seeking secure cloud services to support their need for high-speed data transfer at ultra-low latency. We are excited to open the new Chicago region to help our Midwest customers and partners easily and securely move their mission-critical workloads to the cloud.”

The company also noted its extensive network of more than 75 global and regional OCI FastConnect partners. CoreSite and Digital Realty are the host partners for the new Oracle Cloud Chicago Region’s FastConnect locations. Partners available at launch for the Oracle Cloud Chicago Region include Megaport, Equinix, CoreSite, and Digital Realty.

Currently available Oracle Cloud Regions:

  • Asia Pacific: Tokyo (Japan), Osaka (Japan), Seoul (South Korea), Chuncheon (South Korea), Mumbai (India), Hyderabad (India), Sydney (Australia), Melbourne (Australia), Singapore (Singapore)
  • Americas: San Jose (United States), Phoenix (United States), Ashburn (United States), Chicago (United States), Toronto (Canada), Montreal (Canada), São Paolo (Brazil), Vinhedo (Brazil), Santiago (Chile), Querétaro (Mexico)
  • Europe: Frankfurt (Germany), London (United Kingdom), Newport, Wales (United Kingdom), Zürich (Switzerland), Amsterdam (The Netherlands), Marseille (France), Stockholm (Sweden), Milan (Italy), La Courneuve, Paris (France), Madrid (Spain)
  • Middle East: Jeddah (Saudi Arabia), Abu Dhabi and Dubai (U.A.E), Jerusalem (Israel)
  • Africa: Johannesburg (South Africa)
  • Government: Two general U.S. Government regions, three U.S. Department of Defense specific Government regions, several U.S. National Security regions, and two United Kingdom Government regions (London and Newport, Wales)

 https://www.oracle.com/news/announcement/oracle-opens-cloud-region-in-chicago-2022-12-15/

Thursday, December 15, 2022

Meta halts data center expansion construction in Denmark

Meta has terminated a contract for the expansion of a major data center in Odense, Denmark. 

Per Aarsleff, the lead contractor for project, valued the cancelled contract at DKK 2.4 billion. As a result, all construction work on the data center will be halted immediately. 

https://www.aarsleff.com/about-aarsleff/news/news/termination-of-contract-for-data-centre-in-odense#

Facebook to build Next Data Center in Odense, Denmark

Facebook has selected Odense, Denmark as the location for its next data center, joining Prineville (Oregon), Forest City (North Carolina), Luleå (Sweden), Altoona (Iowa), Fort Worth (Texas), Clonee (Ireland), and Los Lunas (New Mexico) facilities as one of the cornerstones of its global infrastructure. The new data center will be built with Open Compute Project hardware designs and will be one of the most energy efficient to date. The company said...


Tuesday, December 13, 2022

Aligned Data Centers to acquire ODATA data centers in Latin America

Aligned Data Centers agreed to acquire ODATA, a data center service provider offering scalable, reliable, and flexible IT infrastructure in Latin America, from Patria Investments and other selling stakeholders. Financial terms were not disclosed.

In connection with the acquisition, Aligned, which is majority owned by funds managed by Macquarie Asset Management, entered into a definitive agreement to receive a structured minority investment in ODATA from funds managed by SDC Capital Partners.

ODATA operates data centers in Brazil (4), Colombia (1), Mexico (1), and Chile (2).

“The acquisition combines a significant growth runway for expansion and a proven ability to deliver capacity at maximum speed, with regional expertise and partnerships, enhanced fiscal resources, and a resilient supply chain, to deliver a world-class data center platform that meets the demands of our global hyperscale and enterprise customers,” states Andrew Schaap, CEO of Aligned Data Centers. “We’re excited to welcome Ricardo and the ODATA team to the Aligned fold and look forward to fostering our joint commitments to customer centricity and operational excellence as we embark on the next phase of innovation and growth.” 

https://www.aligneddc.com 

Thursday, December 8, 2022

Marvell samples its Spica Gen2 800Gbps PAM4 in 5nm

Marvell Technology has begun sampling its Spica Gen2 800Gbps PAM4 electro-optics platform.

The highly integrated Spica Gen2 platform is built on advanced 5nm process technology with companion transimpedance amplifiers (TIAs) and driver to deliver power savings and advance the transition to 800Gbps networking inside the data center. 

Key features of Spica Gen2 include:

  • Support for 1x800G, 2x400G, 8x100G Ethernet traffic with breakout
  • 25% power savings enabling <12-Watt 800G
  • CMIS compliant with advanced diagnostic features
  • Integration of enhanced optical modulator driver

Spica Gen2 Linear TIAs:

The IN5660TA is a 56GBaud octal channel, linear TIA for PAM4 optical modules. The IN5665TA and IN5669TA are each 56GBaud quad channel, linear TIA offerings. 

Features of the Spica Gen2 linear TIAs include:

  • Wide dynamic range to meet the different link requirements for optical applications
  • Best-in-class linearity, low noise for optimized platform performance
  • Low-power and in bare die form

Spica Gen2 Linear Driver:

The IN5614DV is a 56GBaud quad-channel, linear VCSEL driver for PAM4 optical modules. 

Features include:

  • VCSEL multimode fiber for AOC and transceiver
  • Excellent linearity, high bandwidth, adjustable gain to optimize the PAM4 system performance
  • Low-power driver in bare die form

Marvell said its Spica Gen2 extends the company’s leadership in 800G PAM4 DSPs, building on its Spica DSP announced in 2020 in 7nm as part of the industry’s first 800Gbps PAM4 electro-optics platform. Since that time, the Spica platform has been ramping in artificial intelligence (AI) applications as the demand for higher bandwidth networking infrastructure continues to increase. 

“There is an ever-increasing need for higher bandwidth, lower latencies, and reduced complexities in managing data center infrastructure,” said Xi Wang, vice president of product marketing, Optical Connectivity at Marvell. “With the introduction of the Spica Gen2 5nm optical PAM4 DSP, Marvell is continuing to innovate and enhance the power efficiency with the 800G electro-optics platform while increasing bandwidth in the data center, which is crucial to achieving green and efficient data center architectures. Spica Gen2 enables lower latencies, higher levels of integration, and simplifies switch port management for next-gen cloud data center optical interconnects.”

“Demand for optical technology is expected to grow 14% per year through 2027, primarily driven by the projected sales of 800G and 1.6T transceivers as cloud providers and carriers enhance their infrastructures to meet customer expectations,” said Vlad Kozlov, founder and CEO of Light Counting Market Research. “Spica Gen2 is part of Marvell’s effort to raise the bar in terms of performance, power and TCO to allow clouds to scale.”


CyrusOne aims for carbon neutrality by 2030

CyrusOne has pledged to become climate neutral by 2030, moving up its previous 2040 commitment by a decade.

To achieve this milestone, CyrusOne will continue to improve the energy efficiency of its new and existing data centers, procure renewable electricity at an accelerated rate to power the facilities, and investigate zero-carbon alternatives to traditional diesel backup generators. These efforts build upon the progress CyrusOne has already made, including achieving 100% renewable electricity across its full European portfolio starting in 2021.

“Our customers’ commitments to reduce their carbon footprints has inspired us to quicken our efforts,” said Kyle Myers, Vice President of Environmental Health, Safety, and Sustainability at CyrusOne. “It is becoming more and more evident that our previous target of climate neutral by 2040 was ambitious for its time, but is no longer ambitious enough. We not only plan to reach carbon neutrality by the end of this decade, but to do so while decreasing our water consumption in vulnerable regions.”

https://www.cyrusone.com

Tuesday, December 6, 2022

Digital Bridge completes acquisition of Switch for $11 billion

DigitalBridge and IFM Investors completed their previously-announced acquisition of Switch, which operates a series of high-performance, SuperNAP co-location data centers.

All outstanding common shares of Switch (NYSE: SWCH) were acquired for $34.25 per share in cash, or approximately $11 billion, including the repayment of outstanding debt.

“We are excited to embark on the next chapter of Switch’s evolution in partnership with DigitalBridge and IFM Investors, two leading digital infrastructure investment firms,” said Rob Roy, Founder and Chief Executive Officer of Switch. “With their strategic expertise and financial resources, Switch is ideally positioned to meet growing customer demand for the world’s most advanced and environmentally sustainable data center infrastructure.”

Jon Mauck, Senior Managing Director at DigitalBridge Investment Management, said, “We are delighted to partner with Rob and the Switch team as DigitalBridge continues to grow our portfolio of high-quality digital infrastructure assets globally. With a shared vision for the future of communications infrastructure, Switch, IFM Investors and DigitalBridge are ideal partners, and together we will scale Switch’s business domestically and internationally to meet the robust enterprise demand for mission-critical digital infrastructure.”

Kyle Mangini, Global Head of Infrastructure at IFM Investors, said, “IFM Investors is excited to join DigitalBridge to support Switch in its next phase of growth. Switch’s excellence in data center design and operations, along with its industry leadership in sustainability, makes the company an ideal fit for IFM Investors as we seek to deliver returns to our investors and maximize the retirement savings of the millions of working people they represent.”

http://www.digitalbridge.com

DigitalBridge to acquire Switch for $11 billion for its data centers

DigitalBridge Group agreed to acquire Switch, a leading colocation data center operator, for $34.25 per share in an all-cash transaction valued at approximately $11 billion, including the assumption of debt.Switch, which was founded in 2000, operates SuperNAP data center campuses in Las Vegas, Reno, and Grand Rapids, Michigan. The company touts its high-resiliecy and high-security designs for mission critical workloads in its "Class 5" data centers....

Switch expands data center fleet to 16 with Data Foundry acquisition

Switch agreed to acquire Data Foundry, a carrier-neutral colocation provider with data centers in Austin and Houston, for $420 million in an all cash transaction. The acquisition is expected to close by mid-2021, subject to the satisfaction of customary closing conditions, including regulatory approval. The purchase price of $420 million represents approximately 19x estimated 2021 Adjusted EBITDA, including $2 million of projected run-rate cost synergies. Data...


Monday, December 5, 2022

STACK and ESR to develop data center in Osaka

 STACK Infrastructure and ESR Group announced a joint venture to develop a 72MW data center campus in Osaka, Japan.

STACK and ESR will jointly develop and deliver 72MW of data center capacity in Osaka’s eastern suburb of Keihanna. Construction of the first of three buildings will commence in Q4 2023 and will be ready for service in Q2 2025.

The deal further expands STACK and ESR’s APAC partnership, which currently includes a 48MW data center development in Incheon, Korea.

“Osaka is STACK’s sixth APAC market in 12 months since our entrance into the region, including the expansion of our footprint in both Japan and Australia to over 100MW each,” said Pithambar (Preet) Gona, Chief Executive Officer of STACK APAC. "This campus further deepens our partnership with ESR, allowing us to combine our capabilities to meet our clients’ strategic requirements in existing and emerging Tier 1 data center markets.” 

“ESR’s strong regional development capability in Tier 1 data center markets ensures we are well-positioned to continue to aggressively develop data center facilities across Asia Pacific,” said Diarmid Massey, CEO of ESR Data Centres. “Our partnership with STACK enables us to leverage our respective strengths to target hyperscale customer growth in key markets.”

https://www.stackinfra.com/about/news-events/press-releases/stack-infrastructure-and-esr-expand-their-apac-partnership-into-japan-with-a-72mw-data-center-development-in-osaka/

Sunday, December 4, 2022

Swiss data center operator secures US$512M refinancing

Green, the leading Swiss data center operator, completed a refinancing package valued at CHF 480 million (approximately US$512.3 million) from leading international and Swiss banks. 

Green, which is owned by InfraVia Capital Partners, said the deal will fund the expansion of its current capacity from 33MW to 81MW through the construction of additional capacity in Dielsdorf campus, the expansion of the existing high-performance campus in Lupfig and through opportunities of new campuses in Switzerland.

In the last three years, Green has intensified its cooperation with leading enterprises and public cloud providers (hyperscale companies), invested in sustainable technologies and pioneering innovations and completed new, energy-efficient and high-performance data centers in Zurich and vicinity.

Roger Süess, CEO Green: “With the acceleration of the growth program, Green is responding to the high demand from hyperscale companies who put their trust in Green when it comes to geo-redundant solutions. Green provides space, networks and sustainable growth to the benefit of hyperscale companies, enterprises and Switzerland as a whole.”

https://www.green.ch/en/blog/detail/green-completes-a-chf-480-million-refinancing-and-accelerates-its-investment-programs-in-switzerland

Thursday, December 1, 2022

STACK breaks ground on 7th Northern Virginia data center campus

STACK Infrastructure commenced construction on its latest hyperscale campus in the center of Prince William County in Northern Virginia. Delivery of the first building on the campus is targeted for Q1 2024. The project is STACK's seventh data center campuses in Northern Virginia.

The new 40-acre site will add nearly 100MW of committed and scalable power from Northern Virginia Electric Cooperative (NOVEC). Construction will begin with a 36MW facility, with plans to grow the campus to multiple data centers supported by a 300MW substation.

“Expanding our presence in the heart of Prince William County represents a strategic approach of continuing to deliver scalable capacity where it matters most,” said Matthew VanderZanden, Chief Operating Officer of STACK Americas. “Powered with 100% renewable energy, STACK’s new campus offers a sustainable solution and allows our clients the ability to grow quickly in the world’s largest data center market.”

STACK noted that it nearly 1GW of current and under-development capacity in Norhtern Virginia. 

https://www.stackinfra.com/about/news-events/press-releases/stack-infrastructure-breaks-ground-on-100mw-data-center-campus-in-northern-virginia/

STACK opens 3rd data center in Milan

STACK Infrastructure opened its third data center in Milan (Siziano). The new facility, constructed in less than 12 months on a land parcel it acquired in 2021, brings the company’s live data center capacity in Italy to 120,000 square meters and more than 50MW of power. The new facility runs on 100% renewable energy, utilizes multiple built-in energy-saving features including photovoltaic panels and heat isolation infrastructure, and prequalifies...

STACK Infrastructure builds data center capacity in Australia

STACK Infrastructure announced a partnership with Hickory, a leading Australian commercial real estate developer, to develop data center capacity in three Australian markets: Melbourne, Canberra, and Perth. STACK Australia is currently constructing a 72MW campus in the high growth hyperscale corridor of Truganina in Melbourne’s western suburbs. The facility is expected to be delivered early in 2023 and will include two 36MW buildings (currently...


Wednesday, November 30, 2022

Equinix to build data center in Johor, Malaysia

Equinix unveiled plans to invest approximately $40 million in a new data center located in JOHOR, Malaysia.

The new facility, named JH1, is scheduled to begin operations in Q1 2024, providing 500 cabinets and 1,960 square meters of colocation space. 

The two-story facility will be located at Nusajaya Tech Park (NTP) in Iskandar, Johor. It is 15 kilometers from Singapore, allowing the data center to address excess demand from organizations in the city-state in addition to Malaysian domestic demand.

Equinix also has the option of acquiring additional land in NTP to build a second facility, supporting Malaysia's digital growth aspirations. Companies and multinationals doing business in Malaysia will be able to access Platform Equinix to store and distribute large volumes of latency-sensitive data and applications closer to end users and local markets.

When opened, the new IBX data center in Johor will increase Equinix's total global footprint of more than 245 data centers across 71 metros and 32 countries, providing Equinix's 10,000+ customers more ways to securely deploy, directly connect and effectively scale their digital infrastructure in a rapidly growing economy. It is expected to also present opportunities for further expansion into new metros and market segments in Malaysia.

In Asia-Pacific, Equinix currently has 51 data centers across 13 metros across Australia, China, Hong Kong, India, Japan, Korea and Singapore. In addition, Equinix also announced expansions into Chennai in India, and Jakarta in Indonesia in 2022, strengthening its market leadership in the region.

https://www.equinix.com/newsroom/press-releases/2022/11/equinix-enters-malaysia-with-40m-data-center-investment

Monday, November 28, 2022

AWS promises water replenishment for data centers

Amazon Web Services has committed to become water positive (water+) by 2030, returning more water to communities than it uses in its direct operations. 

The company also announced its 2021 global water use efficiency (WUE) metric of 0.25 liters of water per kilowatt-hour.

The company said it will use sustainable water sources, such as recycled water and rainwater harvesting, wherever possible. In Ireland and Sweden, AWS uses no water to cool its data centers for 95% of the year.

AWS also announced several new projects, which, once completed, will provide more than 823 million liters of water to communities each year, including:

  • India: AWS is providing continued support to WaterAid to complete projects in Hyderabad and Andhra Pradesh after they were launched in March 2022. Since then, WaterAid has already completed five piped water systems and new groundwater recharge projects, which will supply 500 households–approximately 2,100 people–with an estimated 47 million liters of water per year. WaterAid also conducted education campaigns on water conservation in these communities to educate residents on practical ways they can conserve clean water, use rainwater harvesting, and conduct water audits.
  • UK: AWS is working with The Rivers Trust and Action for the River Kennet to create two wetlands on a tributary of the River Thames, one of the most important water catchment areas in the UK. The wetlands will recharge over 587 million liters of groundwater per year and improve water quality by receiving and treating polluted runoff from farms and roadways, addressing growing water scarcity and boosting water quality in the Thames River basin.
  • US (California): Beginning this winter, AWS, the conservation non-profit Freshwater Trust, and the Omochumne-Hartnell Water District will recharge 189 million liters of groundwater per year using winter water from the Cosumnes River. This will allow water to gradually flow through the groundwater table and back into the Sacramento and San Joaquin watershed, increasing water flows during drier summer months. This lowers the temperature of the river, improves salmon habitat, and increases summer flows into the San Francisco Bay Delta, a critical water supply source for the communities in the region.

“Water scarcity is a major issue around the world and with today’s water positive announcement we are committing to do our part to help solve this rapidly growing challenge,” said Adam Selipsky, CEO of AWS. “In just a few years half of the world’s population is projected to live in water-stressed areas, so to ensure all people have access to water, we all need to innovate new ways to help conserve and reuse this precious resource. While we are proud of the progress we have made, we know there is more we can do. We are committed to leading on water stewardship in our cloud operations, and returning more water than we use in the communities where we operate. We know this is the right thing to do for the environment and our customers.”

https://sustainability.aboutamazon.com/water




Tuesday, November 22, 2022

AWS region opens in Hyderabad, India

Amazon Web Services officially opened Asia Pacific (Hyderabad) Region, its second region in India.  The new Hyderabad facility offers three Availability Zones. 

Hyderabad, an important talent hub for IT and entrepreneus, is the capital and largest city in the state of Telangana. 

AWS noted its ongoing expansion in India. The company first established a presence in the country in 2011, with the opening of an office in Delhi.

In 2016, AWS launched the Asia Pacific (Mumbai) Region giving enterprises, public sector organizations, startups, and SMBs access to state-of-the-art public cloud infrastructure. In May 2019, AWS expanded the Region to include a third Availability Zone to support rapid customer growth and provide more choice, flexibility, the ability to replicate workloads across more Availability Zones, and even higher availability.

There are currently 33 Amazon CloudFront edge locations in India: Mumbai, India (10), New Delhi (7), Chennai (7), Bangalore (4), Hyderabad (3), and Kolkata (2) in India. The edge locations work in concert with a CloudFront Regional edge cache in Mumbai to speed delivery of content. There are six AWS Direct Connect locations, all of which connect to the Asia Pacific (Mumbai) Region: two in Mumbai, one in Chennai, one in Hyderabad, one in Delhi, and one in Bangalore.

Finally, the first AWS Local Zones launched in Delhi, India for bringing selected AWS services very close to a particular geographic area. AWS has also announced plans to launch three more AWS Local Zones in India, in the cities of Chennai, Bengaluru, and Kolkata.

https://aws.amazon.com/blogs/aws/now-open-the-30th-aws-region-asia-pacific-hyderabad-region-in-india/

AWS Region opens in Spain

Amazon announced the opening on AWS Region in Aragón, Spain. The regions is officially named Europe (Spain) and the API name is eu-south-2. The AWS Europe (Spain) Region has three Availability Zones (AZ), enabling the deployment of applications across multiple data centers. Each Availability Zone is a fully isolated partition of AWS infrastructure that contains one or more data centers.Availability Zones are separate and distinct geographic...

AWS opens in Zurich

Amazon Web Services officially opened AWS Europe (Zurich) Region.With the launch of the AWS Europe (Zurich) Region, AWS has 90 Availability Zones across 28 geographic regions, with announced plans to launch 21 more Availability Zones and seven more AWS Regions in Australia, Canada, India, Israel, New Zealand, Spain, and Thailand. AWS Regions are composed of Availability Zones that place infrastructure in separate and distinct geographic locations....


Nxtra by Airtel builds hyper scale data center in Kolkata

Nxtra by Airtel, which is a subsidiary of Bharti Airtel, has begun construction on a new hyper-scale data centre in Kolkata. 

The project aims to be the largest data center in east India when it enters service in 2024, representing an investment of Rs 600 Cr. The 25 MW facility in Kolkata at New Town will be a green facility, sourcing clean energy for its operations since its inception. Once ready, it will be Nxtra’s 1st large-scale facility in east India in addition to its already existing 12 large and 120 edge facilities across India, further cementing Nxtra’s position as the nation's largest network of data centres. 

“Nxtra and Airtel are delighted to lead West Bengal's transition into a digital-first economy and would like to thank the state government for their unstinting support. We believe that there is immense potential in the region, our state-of-the-art, carrier-neutral, hyper-scale data centre will not only serve West Bengal but the entire eastern region including north-east and our neighbouring countries, said Mr. Rajesh Tapadia, Executive Director & Chief Operating Officer, Nxtra by Airtel.

Nxtra by Airtel will invest over Rs 5000 cr over the next four years to expand its capacity by 3X to over 400 MW. The company has already invested and partnered with eight organisations to develop renewable energy power plants across India to source more than 180,000 MWh of renewable energy. Nxtra has the ambition to reach net zero by 2031. 

https://www.nxtra.in

Wednesday, November 16, 2022

AWS Region opens in Spain

Amazon announced the opening on AWS Region in Aragón, Spain. The regions is officially named Europe (Spain) and the API name is eu-south-2. 

The AWS Europe (Spain) Region has three Availability Zones (AZ), enabling the deployment of applications across multiple data centers. Each Availability Zone is a fully isolated partition of AWS infrastructure that contains one or more data centers.

Availability Zones are separate and distinct geographic locations with enough distance to reduce the risk of a single event affecting the availability of the Region but near enough for business continuity for applications that require rapid failover and synchronous replication. 

AWS notes that is has had offices in Madrid since 2014 and in Barcelona since 2018 and has a broad network of local partners. 

https://aws.amazon.com/blogs/aws/now-open-aws-region-in-spain/

AWS opens in Zurich

Amazon Web Services officially opened AWS Europe (Zurich) Region.With the launch of the AWS Europe (Zurich) Region, AWS has 90 Availability Zones across 28 geographic regions, with announced plans to launch 21 more Availability Zones and seven more AWS Regions in Australia, Canada, India, Israel, New Zealand, Spain, and Thailand. AWS Regions are composed of Availability Zones that place infrastructure in separate and distinct geographic locations....


Thursday, November 3, 2022

Equinix: major data center builds underway in 31 markets

Equinix's quarterly revenues increased 10% over the same quarter last year to $1.8 billion, or 11% on a normalized and constant currency basis, representing the company's 79th consecutive quarter of revenue growth—the longest streak of any S&P 500 company. Net income amounted to $212 million, a 2% decrease from the previous quarter, primarily due to lower non-recurring xScale® fees, a Q2 favorable tax settlement, partially offset by higher income from operations from strong operating performance and lower net interest expenses.

Charles Meyers, President and CEO, Equinix: "We had another record quarter as global demand for digital infrastructure continues to grow and customer preferences trend convincingly toward architectures that are highly distributed, persistently hybrid, deeply cloud-connected, and increasingly on-demand — all factors fueling our position as a trusted partner in digital transformation. Even in a complex and challenging macro environment, our expansive global reach and robust interconnected ecosystems continue to attract a wide and diverse customer set, as businesses prioritize digital investments and embrace Platform Equinix as a point of nexus to support hybrid and multicloud."

  • Equinix continued to expand its Data Center Services with 46 major builds underway in 31 markets, across 21 countries. Recent activity includes:
  • A $74 million expansion to Indonesia with plans for an International Business Exchange™ (IBX) data center in the heart of Jakarta, scheduled to open by the second half of 2024.
  • A $45 million investment in Colombia for the construction of BG2, Equinix's second IBX data center in Bogotá, scheduled to open in the first half of 2023.
  • The addition of six recently approved projects in Q3 in Barcelona, Milan, Montreal, Jakarta, Silicon Valley and Tokyo.
  • Equinix continues to extend its leadership as the most interconnected platform with four cloud on-ramp wins this quarter bringing Equinix's portfolio to more than 200 on-ramps across 44 markets. Equinix now has 11 metros enabled with five or more on-ramps to the largest cloud players.
  • ~55% of expansion cabinets are in metros that generate >$100M of annual revenues, leveraging established ecosystem density and installed customer base



https://www.equinix.com/newsroom/press-releases/2022/11/equinix-reports-third-quarter-2022-results

Wednesday, November 2, 2022

Co-Packaged Optics (CPO) and Pluggable Summit debate

The future of data center network architecture was the key theme at last week's Co-Packaged and Pluggable Optics Industry Summit, an invite-only event presented by Optica and the Consortium for On-Board Optics (COBO) will host the  at the DuPont Silicon Valley Technology and Innovation Center.

Debate centered on the pros/cons of scaling today switching architecture based on pluggable optical transceivers versus future designs designs with co-packaged optics alongside the switching silicon.

Google: The pluggable design factor for hyperscale data center switches is working well and there is a roadmap to scale for several more generations, said Hong Liu, Google Fellow. Her presentation cited the potential of pluggable interfaces as high as 3.2T OSFP-XD and future 102.4T switch designs. Rather than CPO interfaces on switching silicon, future data center networks could scale using Optical Circuit Switching using MEMS mirror arrays. CPO inside pluggable optical transceiver is beneficial, such as integrating DSPs with TIAs.





Speaking on behalf of Microsoft, Moray McLauren made the case that package-level optical integration (CPO) is needed to (1) address the rising power requirements in data centers ("network power tax is increasing, reducing end user revenue power"), (2) extend radix reach (3) lower component costs (4) drive AI/ML and HPC applications



Meta's Katharine Schmidtke, Director of ASIC and Custom Silicon Sourcing, also presented the case for optical interconnects in AI/ML hardware. As compute fabrics adopt a cluster architecture, the network fabric has to scale. Compared with existing optical modules, CPO promises to significantly reduce the power demands of the new computing clusters.

Power savings in the network can be achieved in other ways, said John Shalf, Lawrence Berkeley National Laboratory.  Think wide and slow! This applies to innovations in (1) in-package integration, (2) DWDM using Silicon Photonics (ring resonators) (3) new comb laser sources capable of generating 100s of frequencies

NVIDIA is moving forward with its own NVLink over optics approach to solve the scaling problem, said Craig Thomson. 


Jeff Maki, Distinguished Engineer at Juniper Networks and Board Member of COBO, presented a taxonomy of 400G and 800G interfaces. 

Arista's Andy Bechtolscheim presented the strongest case that pluggables are the best solution for Ethernet data center switching and that CPO switches fall short in time-to-market, standardization, break out connectors and a host of other issues.  Potential applications for CPO might include copackaging with DSPs inside pluggable modules at 224G and non-Ethernet uses cases such as AI chips.


Pluggable optics remains a feasible and dominant use case for the next generation of switching said Cisco's Anthony Torza.

It is all about system level power, said Infinera's Dave Welch. Through its vertical integration, Infinera already offers a 400G ZR+ pluggable module with a 1600km range. For intra data center range, innovations such as the microLED technology developed by Avicena promise very significant power improvements with integration in CMOS.



Marvell's Radha Nagarajan offered some thoughts on heterogeneous integration including improved modulation that puts us on the path to 3.2T.